Project |
3D Modular Schools |
Year Completed |
2020 |
Location |
Griffeen, Lucan, Co. Dublin |
Design |
NZEB Complaint 9000 sq ft school – constructed using 3D volumetric modules including nine classrooms, a corridor, staffroom and toilets. Bespoke design to cater for Covid-19 handwashing facilities. All modules constructed in our ISO factory controlled environment. |
Project Delivery |
Project delivered in a 12 week period from order to install – 3 weeks to finalise bespoke design, and 9 weeks from design approval to completion and handover. |